There are several approaches to constructing a building. Using a design-build or construction management approach means the contractor will already be well-versed in your project. In a traditional design-bid-build process, the project is put out to bid, and a general contractor is selected according to pre-established factors, such as experience, schedule, and cost.
During the construction phase, the goal of the project team is to monitor the implementation of the design into construction to ensure that the original intent has not been compromised. Activities occurring during construction that are led by the healthcare organization include: launching internal readiness and process improvement plans, obtaining zoning and use permits, establishing early permit and third party approvals, and beginning transition planning, and obtaining the Certificate of Occupancy (CO).
Activities developed during this phase that are design team-led processes include: coordinating construction administration documents, developing punch lists, and completing project close-out.
The team should monitor implementation of design (Step Seven) to ensure EBD innovations are implemented as envisioned during the design phase.
There are two types of Construction Managers (CMs). Through an agency CM, construction cost management is a fee-based service in which CM is responsible exclusively to the owner and acts in the owner's interests at every stage of the project. The construction manager offers advice on matters such as:
An Agency CM provides management of every stage of the project, beginning with the original concept and project definition and can represent the owner by helping to select the design team as well as the construction team and manage the design preventing scope creep, helping the owner stay within a pre-determined budget by performing Value Engineering, Cost/Benefit Analysis and Best Value Comparisons.
A second type of CM is a CM at-risk. This is a delivery method which entails a commitment by the construction manager to deliver the project within a Guaranteed Maximum Price (GMP. The construction manager acts as consultant to the owner in the development and design phases, (often referred to as "Preconstruction Services"), but as the equivalent of a general contractor during the construction phase. When a construction manager is bound to a GMP, the most fundamental character of the relationship is changed. In addition to acting in the owner's interest, the construction manager must manage and control construction costs to not exceed the GMP. (Source: adapted from http://en.wikipedia.org/wiki/Construction_management)
Operational readiness includes:
Related activities include a change readiness assessment that can be conducted to understand barriers to change. This includes which stakeholder groups are most resistant to change, their specific concerns, and how those concerns can be addressed. It also provides a quantitative measure to monitor readiness and alignment over time