A free resource from Capital Link and Primary Care Development Corporation on developing a health center. Phases and Activities applicable to this resource include:
Organizational Readines
- Conduct operational planning
- Conduct allocation planning/preliminary space assessment
- Finalize strategic planning
- Create project organizational leadership
- Development of project budget
- Explore various financing options
- Consider sites (see chapter 5)
- Develop a preliminary project schedule (see chapter 2, and Appendix B)
- Hire a project manager and architect
Pre-Design
- Determine financial feasability
- Select/survey sites and evaluate space availability (see chapter 5)
- Select an attorney, architect/interior designer, contractor and construction manager (see chapter 3-4, 6 and Appendix D)
- Establish the remaining project team (see chapter 4, Appedix D and E)
- Property aquisition/site control
- Plan and program
- Refine project budget/schedule
- Start conceptual diagraming
Design
- Continue conceptual diagraming
- Schematic design
- Design development
- Construction documents
- Bid and award - this may be phased based on project type (see chapter 7)
Construction
- Notice of completion
- Final completion
- Transition planning