Substantial Completion (C,D)

Substantial completion is evaluated by the architect and is where the Owner assumes responsibility for the building. It is set from the beginning of construction, and is significant as it is a transfer point of risk and liability from the Contractor to the Owner. It is the beginning of project closeout, but work is still required, such as punch list items.